Fencing works on strata or community title common property in SA: who to coordinate with, keeping residents' paths open, and where the gates go.

Temporary mesh fencing closing off a works area beside a low-rise apartment block, with the residents' path left open

BoltHire Team

Fencing building works on strata or community title land in South Australia starts with permission, not panels. The common property belongs to the corporation, not to any one owner, so you need the corporation's agreement, or the agreement of a manager acting within its delegation, before the line goes in. Our hire terms ask you to confirm you are entitled to have the fence where you mark it. After that the job is practical: close the works area, keep residents' paths open, and put the gates where people actually walk.

This page covers that sequence for works on apartment blocks, townhouse groups and other strata or community schemes. It gives a light outline of the law from official sources. It is not legal advice, and it does not cover disputes between owners.

Why common property changes the fencing question

On a house block, the person ordering the fence usually controls the land. On a strata or community scheme, the driveway, the paths and the gardens are often common property. Check the registered plan and scheme type: building exteriors may be common property in a strata scheme, while buildings within lots in a community scheme are generally the lot owners' to maintain.

The Strata Titles Act 1988 says it directly: "The common property is held by the strata corporation in trust for the unit holders" (section 10). The Act lists the corporation's first function as "to administer and maintain the common property for the benefit of the unit holders" (section 25). Community title schemes run under the Community Titles Act 1996, which gives a community corporation the function "to administer, manage and control the common property for the benefit of the owners of the community lots" (section 75).

For fencing, that means one thing. A fence on common property sits on land the corporation controls. Our hire terms ask you to confirm you are entitled to have the equipment installed where you have marked it. On common property that entitlement comes from the corporation.

Who to coordinate with

Start with the corporation, then work outward. The usual parties are:

  • The strata or community corporation. It controls the common property. Agree the fence line, the dates and the gate positions with it.
  • The strata manager, if there is one. Under section 27A of the Strata Titles Act a corporation can delegate tasks such as "arranging for the maintenance and repair of the common property". A manager acts only within what the corporation has delegated.
  • The residents. They are the people walking past the line every day. Tell them where the works area is, how long it stays, and which path to use.
  • The council, if the line leaves the boundary. A fence on the footpath or verge is also a council permission question.
  • Whoever certifies the works. Building approval for the works sits with the council or building surveyor. That is separate from the fence.

One limit is worth knowing early. Section 27A(4) of the Strata Titles Act says a corporation cannot delegate a power that it can only use by special or unanimous resolution. If the works need a special or unanimous resolution, the manager cannot sign them off alone.

When the works are one owner's renovation

Sometimes the works belong to one unit owner, such as an extension or a change to the outside of a unit. Section 29 of the Strata Titles Act generally requires that kind of work on a unit to be authorised by special resolution of the strata corporation, with limited exceptions. Sort out the authority for the works first. The fence follows the works, so book it once the works are approved.

Keeping residents' access open

A strata site is an occupied site. That is the main way it differs from a new build. People who are not part of the job will be inside the area the job uses: residents collecting mail, putting bins out, walking to the car park, or coming home after dark.

The SA government summary of strata articles lists "not obstructing the common areas" among the rules owners follow. A works fence will block part of the common area while it stands. The aim is to block only the part the work needs and to leave a usable way around it.

Four habits keep the line workable:

  1. Fence the works area, not the whole property. Draw the line around the hazard. Leave the entrances, letterboxes, bin store and parking outside it.
  2. Plan the residents' route before the fence line. Decide where people will walk, then draw the fence to leave that path clear. If you are not sure how many panels the works area needs, how many temporary fence panels do I need walks through the count. Check that the route works for a pram, a wheelchair or someone carrying shopping.
  3. Keep the line continuous. A works area next to an occupied building has to stay closed. A panel moved for a shortcut is a gap.
  4. Keep the access you gave on install day. The crew needs clear vehicle access to the line on install day and collection day. On a shared driveway, agree that with the corporation and residents ahead of time.
A pedestrian gate in a temporary mesh fence line beside a shared driveway at a low-rise apartment block

Where the gates go

On an occupied site, a gate in the wrong place gets bypassed. If the gate is not on the route people already use, a panel is moved within a week, and the line is no longer closed.

Put gates in two kinds of places:

  • Trade gates where the workers and deliveries enter the works area. Keep them shut when the site is unattended.
  • Pedestrian gates only where a resident path has to cross the line, and only after the contractor has set up a separately protected route. A gate never makes it safe to walk through an active work or falling-material zone. Often the better choice is to move the line so residents never need to open a gate at all.

On a strata job, write the gate positions into what you agree with the corporation. Residents should not discover on the morning that their usual path now ends at a locked gate. On the quote, gates are counted as their own items and show on the line before you pay.

Common strata works and how the fence fits

Facade, roof and balcony work

Repairs to external walls, roofs and balconies are usually common property work arranged by the corporation. The hazard is falling material. Fence the drop zone under the work, and keep the residents' entry outside it or covered by a separate route.

Driveway, paving and services work

When the shared driveway or paths are dug up, the fence moves with each stage. Plan the stages with the corporation so one way in and out stays open throughout. Redraw the line for each stage; the price updates with the setup.

Car park and garden works

These often run for weeks with nobody on site at night. The line has to stay closed after hours. Where children live in the complex, the standard rises: a continuous line, nothing climbable stacked against it, and gates that actually close.

FAQs

Can the strata manager approve a temporary fence on common property?

If the corporation has delegated that task, the manager can arrange it on the corporation's behalf. A manager cannot exercise a power that needs a special or unanimous resolution. Ask the manager what has been delegated before you book.

Does a temporary fence need council approval on a strata site?

Not usually while it stays inside the property boundary. Once the line goes onto the footpath or verge, occupying that land generally needs council approval and a plan for pedestrians.

Who pays for fencing on strata common property?

That depends on whose works they are and what the corporation decides. Agree it in writing with the corporation before the fence is booked, so the person on the order is the person paying.

What should we tell you about a shared driveway?

Tell us about underground or overhead services, recent excavation and restricted vehicle access before install day. These change where feet and stays can safely go.

Is there a cash bond on the fence?

No separate cash bond. You pay the installed price for the period you book. On card-paid orders, the card stored with Stripe covers panels that are damaged, lost or not returned. Approved invoice accounts follow their agreed terms.

In short

On strata and community title land, get the corporation's agreement on the line, the dates and the gates before you book. Then fence the works area tightly, keep residents' paths outside it, and put gates where people already walk. Draw the line on the quote to see the installed price. The renovation fencing page covers occupied sites in more detail, and the council permits guide covers lines that reach the footpath.