Knock Down Rebuild Fencing in Adelaide
How the temporary fence line changes on an Adelaide knockdown rebuild, from demolition to handover, and how to book one hire that follows it.

BoltHire Team
On a knockdown rebuild the fence is not one installation. It is one hire that changes shape at least three times: around a house coming down, around an empty block, then around a new house going up. The safest way to fence a knockdown rebuild in Adelaide is to book one line through all of those stages, under one name, and redraw it as the site changes instead of taking it down between contractors. This page covers that thread from demolition to handover. It does not repeat what the demolition stage or the build stage each need on their own. Those are on demolition site fencing and new home build fencing.
Why a knockdown rebuild is its own fencing job
A new build on a vacant block starts with nothing to remove. A demolition job ends when the block is clean. A knockdown rebuild is both, back to back, usually with two different businesses on site: a demolition contractor, then a builder.
That handover is where fencing goes wrong. The demolition contractor's fence leaves with their crew. The builder's fence arrives with the slab. In between sits the flat, cleared, open block. The demolition page calls that gap the moment of highest risk for unauthorised entry. On a knockdown rebuild it is built into the program.
Key facts for a knockdown rebuild fence
- One order, many shapes: the line can be redrawn from the order page as stages change, and the updated figure shows before you confirm.
- Adding panels keeps the existing line: adding panels mid-hire does not re-quote the line already installed.
- Hire lengths: hire is priced by the week, and you can book by the week or by the month in the quote. A knockdown rebuild usually suits a long booking rather than repeated short ones.
- What the price includes: hire, delivery, installation and collection, GST included, with no cash bond added at checkout.
- Footpath approvals: if the line goes onto the footpath, verge or road reserve, that approval is yours to obtain. We supply and install the fence.
The stages, and what happens to the line
Before the demolition
Decide who holds the fence. If the demolition contractor brings their own and the builder brings another, someone has to cover the gap. Our hire terms put the order in the name of the customer named on it. On many knockdown rebuilds the simplest holder is the owner or the builder, booking from the first day of demolition to handover.
Draw the demolition line first. It is usually the widest: the whole block, with bracing for a line that machines work beside. The demolition site fencing page covers denser bracing, hoarding and chutes, and why the exclusion zone moves as the house comes down.
The cleared block
When the slab and footings are out and the block is flat, nothing on site looks dangerous. Holes from old footings, service pits and loose fill say otherwise. SafeWork SA's site security guidance sets out how the need for a fence depends on risk. A suburban single-storey job "with no excavations" may not need a secure access system, but bunting or plastic strips "do not prevent access". A cleared knockdown block with open pits is not the low-risk case.
Keep the line closed through this stage. If the gap between contractors is weeks rather than days, that is still fence time. Collection is a date on the order, not something that happens because one crew leaves.
Site start for the new house
The builder's layout rarely matches the demolition layout. The laydown area moves. The site toilet arrives. A neighbour's fence may come down for a new boundary wall. Redraw the line on the order page to match. The new home page explains why the line in week one is rarely the line in week twelve.
Frame to lock-up
This is the long middle, and the stage where the line drifts if nobody owns it. Trades open a panel and do not close it. Bricks end up stacked against the mesh. Keep the line continuous, keep gates closed when the site is empty, and do not stack materials against the fence. Those are already conditions of the hire.
Landscaping and handover
The fence usually comes down last. Driveways, crossovers and paths go in near the end, often where the gate stood. Plan the gate's final move before the concrete is booked, not on the morning of the pour.

Gates move more than once
On a knockdown rebuild the vehicle gate often changes position. Demolition trucks and bins come in where the old driveway was. The new house may put the crossover somewhere else. Concrete, frames and trusses come in wherever the builder sets up.
When you draw the first line, put the gate where the demolition trucks will come in. When the builder's access is known, move it. A gate in the wrong place gets opened by hand for months, or left open. Pedestrian gates are sized for people. Vehicle gates are sized for trucks. Both appear on the line before you pay.
The footpath, the verge and the street
An older house often sits close to the street, and demolition can push work onto the verge: a skip, a chute base bin, a temporary crossing. The first question is whether the line stays inside your boundary. If it does, you avoid the permission step. If it does not, the council permits guide explains who to ask and what they want, especially the plan for pedestrians. Apply before you book the install date, not after.
For the rebuild stage, check the line again. A footpath line that suited the demolition may not be needed for the build, and taking the fence back inside the boundary removes the question.
Planning the hire length
Add up the stages, not just the build contract. Demolition, the gap, the build to lock-up, the fit-out, the landscaping. For many Adelaide knockdown rebuilds that is most of a year or more. Book a period that covers it rather than stacking short hires. The hire period guide goes through the options. If the program runs past the collection date, extend from the order page.
If you finish early, collection can move forward, and charges stop at the collection date, subject to any minimum on the order. Booking a long period is not a promise to keep the panels longer than the site needs them.
Other items that follow the stages
- Rubbish chutes for a two-storey demolition or an upper-floor strip-out, quoted by our team by level. See rubbish chute hire.
- Ground protection mats under an excavator or crane crossing the verge or a new driveway, arranged by our team.
- A pool barrier if the rebuild includes a pool. That is a separate fixed 8-week package inside the site fence, quoted by our team.
FAQs
Can the demolition contractor and the builder use the same fence?
Yes, if one person holds the order. The line is redrawn between stages instead of being collected and installed again. Agree early who books it and whose card sits behind it.
Who is responsible for the fence between contractors?
The customer named on the order is responsible for the equipment from install until collection, including theft and damage by others. Ordinary site wear is in the damage waiver. That is another reason to settle who holds the order before demolition starts.
What if the demolition start is delayed before install?
You can change or cancel the order free of charge up to the cutoff shown on it for the install date. After the cutoff the load is already allocated, so a cancellation may be charged the delivery component for your zone.
Can the street frontage have hoarding during demolition?
Hoarding is not in the online quote. Our team arranges hoarding runs; tell us the frontage and the dates. Mesh suits most demolition sites, and hoarding goes where dust, sightlines or the street frontage matter, or where the council or principal nominates it.
Can the fence stay up while the block sits empty waiting for approvals?
Yes. It stays until the collection date on the order. If the wait runs longer than planned, extend from the order page.
In short
A knockdown rebuild needs one fence that follows the site through demolition, the empty block and the new build. Decide who holds the order, keep the line closed between contractors, move the gate when access moves, and book a period that covers the whole program. Draw the first line on the quote and see the installed price.