Temporary Fence Installation, Step by Step
How a temporary fence is installed in Adelaide, from loading the truck to the last clamp, and what to sort out on site before the crew arrives.

BoltHire Team
A temporary fence is installed in a fixed order: the line is checked against the plan, each panel goes into its feet, the joins are clamped, and stays brace the run against wind. Nothing is dug into the ground. The fence holds because of its feet, its clamps and its bracing working together. This article walks through an install day as it happens on an Adelaide site, using photos from a recent BoltHire job. It covers mesh construction fencing, not pool fencing or crowd control barriers.
The install in five steps
- The line is measured first. The crew measures the line you drew before the gear comes off the truck. If the line on site is within 5% of your map measurement, the price stands.
- Every panel stands in feet. Each panel leg drops into a foot. Neighbouring panels share a foot, so the line is continuous.
- Every join is clamped. A clamp locks each pair of panels together at the join, so the run moves as one fence, not as loose panels.
- Stays brace the run. Stays are angled braces that hold the line upright against wind. How many a run needs depends on its length, its exposure and anything hung on the mesh.
- Gates go where the access is. Pedestrian and vehicle gates sit in the line where people and vehicles actually need to get through.
With BoltHire, these are not choices made on the day. Gates, corners and bracing show on the line before you pay, and the crew works to that line as the install plan.
Before the truck leaves
The install starts in the yard. Panels, feet and clamps are counted onto the truck against your drawn line, so what arrives matches the fence you ordered.

On the drive in, panels are stacked flat and strapped down. You get a text when the crew is on the way.
On site: measuring the line
The first job on arrival is checking the ground against the plan. The crew measures the line you drew, on the ground.
Under BoltHire's terms, you are responsible for telling us about underground or overhead services, recent excavation, and anything else on site that changes where a foot or a stay can safely go. Tell us at booking, not on the day. A foot or a stay that has to move can change how the line runs.
Setting the feet and panels
Temporary fence feet are the base of the whole system. Each foot has two holes. The end leg of one panel and the start leg of the next drop into the same foot, which is why a hired fence counts one foot and clamp set per panel.

Our mesh panels are 2.1 metres high. The crew stands each one in its feet and lines it up with the last, following the line you drew.
Feet spacing follows the panels. Because each foot takes two legs, the feet sit one panel apart all along the line. The surface matters too: feet behave differently on concrete, compacted gravel and soft or sloping ground. Our wind rating guide covers how the surface changes what a fence can resist.
Clamping the joins
Once two panels stand side by side in a shared foot, a clamp goes around both uprights and is tightened. This is the step that turns a row of panels into a fence. A line with loose joins can be lifted apart or pushed over one panel at a time. A clamped line resists as one.
Bracing the run
Stays are the angled braces you can see standing off the fence in the hero photo above. A stay attaches to the panel and is held down at its base, so it stops the panel tipping in the direction of the wind.
How many stays a run needs is not a guess made on the day. BoltHire's quote counts braces off three things:
- the run length;
- how exposed the site is;
- anything you hang on the mesh, such as shade cloth or a banner.
Our pricing tool shows the standard setting as one stay per six panels, and adds more where the run needs it. Shade cloth and banners catch far more wind than bare mesh, so ticking them in the quote changes the bracing in the same quote.
Our temporary fence wind rating guide explains why corners, free ends and gates are the points that need the most attention.
Gates and the finished line
Gates go in the positions marked on your plan. Pedestrian and vehicle gates are sized to what has to get through. Put them where the access actually is, and the line closes itself after every trip.
When the crew leaves, the line is installed as planned: feet spaced, clamps tight, stays braced. The fence that stands at the end is the one you saw on the map when you booked.
What happens after install day
The fence stays up for the term you booked, with hire charged by the week. To change the end date, book a later or earlier collection from the order page. The updated weekly figure shows before you confirm.
On the off-hire date on your order, the crew comes back and collects the fence. Collection is already in the installed price. How long to book for is covered in our article on temporary fence hire periods.
Frequently asked questions
Is installation included in the temporary fence hire price?
Yes. The installed price on screen covers hire, delivery, installation and collection, GST included. There is no separate cash bond on top of it.
Can I install temporary fencing myself?
Hired fencing is installed and collected by our crew. If you buy panels outright, they are delivered to your site. If you want our crew to install a purchase, talk to our team and we will set it up.
When can the fence be installed?
You pick the install day when you book, and it is written on your order. The days offered come from our actual run schedule. Install days are business days.
Can the fence line be changed after it is installed?
Yes. Add panels or move the line from the order page. The new figure shows before anything is booked.
Do I need a council permit for a temporary fence?
Inside your own boundary, it is mostly a safety question. Once the fence steps onto the footpath, verge or road reserve, you are occupying public space, and the approval normally comes from the council for that street. Our guide to council permits for temporary fencing in SA explains when one is needed.
In short
A temporary fence goes in as feet, panels, clamps and stays, in that order, to a line that was measured before the gear came off the truck. Drawing the line on the map first is what lets the gates, corners and bracing be settled before install day. Price your installed fence or see how temporary fencing hire in Adelaide works.